The Fort Belvoir Community Hospital presentation and the BIO Update presentation from the June 30, 2009 Public Information Meeting are available online.  Don’t forget to check out the July 2009 issue of the newsletter, which includes the current status relative to several BRAC projects!  Please contact us for more information or to be added to our mailing list.

Fort Belvoir's Transformation:
Making the Vision Real  

 

Fort Belvoir Community Hospital

  • A new 120-bed hospital at Fort Belvoir is being constructed on the Main Post and is replacing the DeWitt Army Community Hospital.

  • Construction of the 1.3 million square foot complex is approximately 33% complete and is scheduled to be completed in Spring 2011.
 

 National Geospatial-Intelligence Agency (NGA)

  • Groundbreaking for NGA’s new $1.8 billion facility, which is referred to as New Campus East (NCE), occurred in September 2007.

  • Construction of the 2.4 million square foot building is approximately 25% complete and is scheduled to be completed in Spring 2011.


Please see the July 2009 issue of the newsletter for additional information regarding the status of these projects, as well as several other projects included in Fort Belvoir’s implementation of the Base Realignment and Closure Act of 2005 (BRAC).